A feature atrium that cannot be reached from the floor
9,200 m² eight-storey headquarters, full-height glazed atrium, polished stone floor.
- Design decision
- High-level glazing and balustrades specified with no permanent access provision.
- Friction created
- Access friction. Every high-level clean needs a MEWP, out of hours, with the atrium closed.
- Operational and human consequence
- Cleaning falls to a quarterly specialist visit. Between visits the building looks unclean at its most visible point.
- Cost consequence
- Access premium dominates the model; the atrium alone carries a larger premium than the whole ground floor.
- Could it be designed out?
- Permanent anchor points and a reachable maintenance walkway designed in at Stage 4.
- Value of fixing it
- The specialist visit reduces to an annual inspection and the in-house team holds the standard between times.
Illustrative — costs modelled from stated assumptions, not a real contract.